Item 105 – SUBGRADE PREPARATION
105.1 Description
This Item shall consist of the preparation of the subgrade for the support of overlying structural layers. It shall extend to full width of the roadway. Unless authorized by the Engineer, subgrade preparation shall not be done unless the Contractor is able to start immediately the construction of the pavement structure.
105.2 Material Requirements
Unless otherwise stated in the Contract and except when the subgrade is in rock cut, all materials below subgrade level to a depth 150 mm or to such greater depth as may be specified shall meet the requirements of Section 104.2, Selected Borrow for Topping.
105.3 Construction Requirements
105.3.1 Prior Works
Prior to commencing preparation of the subgrade, all culverts, cross drains, ducts and the like (including their fully compacted backfill), ditches, drains and drainage outlets shall be completed. Any work on the preparation of thesubgrade shall not be started unless prior work herein described shall have been approved bythe Engineer.
105.3.2 Subgrade Level Tolerances
The finished compacted surface of the subgrade shall conform to the allowable tolerances as specified here under:
Permitted variation from +20mm
design LEVEL OF SURFACE -30mm
Permitted SURFACE IRREGULARITY
MEASURED BY 3-m STRAIGHT EDGE 30 mm
Permitted variation from
design CROSSFALL OR CAMBER +/-0.5%
Permitted variation from
design LONGITUDINAL GRADE +/-0.1%
over 25 m length
105.3.3 Subgrade in Common Excavation
Unless otherwise specified, all materials below subgrade level in earth cuts to a depth 150 mm or other depth shown on the Plans or as directed by the Engineer shall be excavated. The material, if suitable, shall be set side for future use or, if unsuitable, shall be disposed off in accordance with the requirements of Subsection 102.2.9.
Where material has been removed from below subgrade level, the resulting surface shall be compacted to a depth of 150 mm and in accordance with other requirements of Subsection 104.3.3. All materials immediately below subgrade level in earth cuts to a depth of 150 mm, or to such greater depth as may be specified, shall be compacted in accordance with the requirements of Subsection 104.3.3.
105.3.4 Subgrade in Rock Excavation
Surface irregularities under the subgrade level remaining after trimming of the rock excavation shall be leveled by placing specified material and compacted to the requirements of Subsection 104.3.3.
105.3.5 Subgrade on Embankment
After the embankment has been completed, the full width shall be conditioned by removing any soft or other unstable material that will not compacted properly. The resulting areas and all other low sections, holes, or depressions shall be brought to grade with suitable material. The entire roadbed shall be shaped and compacted to the requirements of Subsections 104.3.3. Scarifying, blading, dragging, rolling, or other methods of work shall be performed or used as necessary to provide a thoroughly compacted roadbed shaped to the cross-sections shown on the Plans.
105.3.6 Subgrade on Existing Pavement
Where the new pavement is to be constructed immediately over an existing Portland Cement concrete pavement and if so specified in the Contract the slab be broken into pieces with greatest dimension of not more than 500 mm and the existing pavement material compacted as specified in Subsection 104.3.3, as directed by the Engineer. The resulting subgrade level shall, as part pavement construction be shaped to conform to the allowable tolerances of Subsection 105.3.2 by placing and compacting where necessary a leveling course comprising the material of the pavement course to be placed immediately above.
Where the new pavement is to be constructed immediately over an existing asphalt concrete pavement or gravel surface pavement and if so specified in the Contract the pavement shall be scarified, thoroughly loosened, reshaped and recompacted in accordance with Subsection 104.3.3. The resulting subgrade level shall conform to the allowable tolerances of Subsection 105.3.2.
105.3.7 Protection of Completed Work
The Contractor shall be required to protect and maintain at his own expense the entire work within the limits of his Contract in good condition satisfactory to the Engineer from the time he first started work until all work shall have been completed. Maintenance shall include repairing and recompacting ruts, ridges, soft spots and deteriorated sections of the subgrade caused by the traffic of the Contractor’s vehicle/equipment or that of the public.
105.3.8 Templates and Straight-edges
The Contractor shall provide for use of the Engineer, approved templates and straight- edges in sufficient number to check the accuracy of the work, as provided in this Specification.
105.4 Method of Measurement
105.4.1 Measurement of Items for payment shall be provided only for:
1. The compaction of existing ground below subgrade level in cuts of common material as specified in Subsection 105.3.3.
2. The breaking up or scarifying, loosening, reshaping and recompacting of existing pavement as specified in Subsection 105.3.6. The quantity to be paid for shall be the area of the work specified to be carried out and accepted by the Engineer.
105.4.2 Payment for all work for the preparation of the subgrade, including shaping to the required levels and tolerances, other than as specified above shall be deemed to be included in the Pay Item for Embankment.
105.5 Basis of Payment
The accepted quantities, measured as prescribed in Section 105.4, shall be paid for at the appropriate contract unit price for Pay Item listed below that is included in the Bill of Quantities which price and payment shall be full compensation for the placing or removal and disposal of all materials including all labor, equipment, tools and incidentals necessary to complete the work prescribed in this Item.
Payment will be made under:
Pay Item Number | Description | Unit of Measurement |
---|---|---|
105 (1) | Subgrade Preparation (Common Material) | Square Meter |
105 (2) | Subgrade Preparation (Existing Pavement) | Square Meter |
105 (3) | Subgrade Preparation (Unsuitable Material) | Square Meter |