ITEM 415 - ELASTOMERIC, HOT-APPLIED JOINT SEALANT WITH SINGLE-SIZED AGGREGATES FOR BRIDGE EXPANSION JOINTS
415.1 Description
This Item shall consist of furnishing and placing elastomeric, hot-poured
joint filler with single-sized aggregates in bridge expansion joints in
accordance with this Specification and as shown on the Plans, or as
directed by the Engineer.
The joint filler combines an elastomer modified bitumen binder and selected
single-sized aggregates for the strength and flexibility of the joint. It
accommodates up to ±25 mm movement in horizontal direction but it can move
in all directions. The joint is constructed in-situ and is a hot process.
415. 2 Material Requirements
415.2.1 Bituminous Materials
The binder is an elastomer-modified bitumen, formulated to combine good
fluidity for the installation process and flexibility with the following
properties:
Properties
|
Requirement
|
Test Method
|
Softening point, 0C
(Ring & ball method) Flow resistance @ 600C, mm Cone penetration @ 250C, 150g, 5 sec.; dmm Safe heating temp. 0C Pouring temp, 0C Safe heating time, hr. |
95 to 115
5 max.
10 – 30
220 max.
190 to 210
7 max.
|
ASTM D 36 or AASHTO T 53
ASTM D 1191 or AASHTO T 187
|
415.2.2 Aggregates
Aggregates are single-sized stones normally chosen from the Basalt, grit
stone, gabbros or granite group. The use of a single aggregate enables a
higher binder content to be reached. It will also ensure a constant ratio
of stone to binder. This is important to give the joint its optimum
combination of flexibility and load bearing capacity.
Joint Depth
|
Stone Size
|
50 mm to 75 mm
76 mm to 100 mm
|
14 mm or 20 mm
20 mm
|
415. 2.3
Caulking
- Premolded expansion joint filler (sponge rubber type) conforming to
AASHTO M 153.
415.2.4 Steel Plate
- Use appropriate size of plate based on plate selection table. Material
shall be A 36 conforming to AASHTO M 270.
415.3 Construction Requirements
The binder fills the gap and the voids between the single sized aggregates.
Its purpose is to impart flexibility to expansion joint so that it
accommodate the various movements of bridge.
415.4 Installation Procedure
1. Layout - In case the trenches are not preformed, joints are laid out on
the site by locating the exact gap opening and measuring 250 mm on both
sides from the center of the gap. The center of the layout shall be the
center of the gap. Chalk-mark both sides of the joint width. Cut the full
depth using a concrete cutter. A strict minimum of 50 mm depth is observed,
in cases where there is wearing course and the thickness is less than 50
mm, the deck shall be chipped upon the approval of the bridge engineer to
attain the required minimum depth. After cutting the full depth of the
joint, break the joint location by using a jackhammer. Remove all broken
slabs to open a trench. The side wall shall also be free from loose debris
and shall at least be at right angle with the exposed deck.
2. Cleaning - Clean the trench thoroughly by using compressed air to remove
all visible dusts. It is best wire-brush the sides of the trench as well as
the de remove all loose particles.
3. Installation of Premolded Joint filler - Install a compressible
premolded rubber type joint filler on the trench gap. Make sure that the
premolded expansion joint filler was installed approximately 25 mm below
the deck level at 25% minimum compression to allow the binder to fill the
top portion and prevent from falling.
4. Hot Air/Flame Cleaning/Pre-heating - The trench is then cleaned and
pre-heated by using hot compressed air. This shall remove all remaining
debris and will completely clean and heat the trench to prepare it for
priming.
5. Priming - Heat the binder to its working temperature of 190°C to 210°C.
When the binder is ready for use, prime the trench with the binder. Ensure
that all surfaces are evenly covered with binder. Ensure that the top of
the premolded expansion joint filler is also filled with binder up to the
deck level.
6. Plating -Cover the top of the gap. Position the plate cover on the
center of the gap and fix it with locating pin. In small joint gaps, the
primary purpose of the plate is to prevent the binder from continuously
flowing to the gap during priming. However, in case where the joint gap
exceeds 30 mm in width, the plate shall be of importance to distribute
vehicular loading.
7. Plate Priming - Pour binder on top of the plate and ensure that all the
surface of the steel plate, including its sides are covered with binder.
8. Stone Laying Prepare the pre-washed aggregates (normally gabbros or
granite family), by putting it inside a mixing tub. Heat the aggregates
while the tub is rotating until it reaches the working temperature of 150°C
to 180°C.
A premix of one layer of aggregates can be put in the trench. Rake the
aggregates to spread it evenly on the trench. Make sure not to lay the
stone more than 25 mm thick per layer.
Aggregates size are normally 14 mm or 20 mm in diameter, depending on the
size of the joint, pre-washed, clean and packed in 20 kg to 23 kg.
9. Binder Pouring - Pour the binder on top of the stone layer. Rake the
stones to spread it evenly on the trench. Ensure that each stone is covered
with binder and the aggregates are in contact with each other. Pour binder
to the trench and repeat stone laying and the binder pouring process until
the stone and binder layer are approximately 20 mm to 25 mm below the
wearing surface.
10. Topping - Prepare a premix of binder and stone in the tub on a 6:1
approximate proportion. Keep the mixing tub rotating while pouring the
premix inside the tub. Make sure all aggregates are suitably covered with
binder. Pour the premix on top of the joint to a level of approximately 20
mm above the wearing surface.
11. Compaction - Wait for the temperature to drop about so0c, then, using a
vibratory plate compactor, compact the finished expansion joint to level
the joint with the wearing surface. Make multiple passes to ensure that the
joint is properly compacted. This will prevent the joint from setting on
the later stage after opening to traffic.
12. Top Screed Surface - After compaction, prepare a binder topping and
pour the heated binder on top of the compacted joint. Wearing a heavy-duty
heat resistant hand gloves, manually screed the topping. Avoid too thick
binder topping (recommended thickness is about 2 mm to 3 mm) and ensure
that there are visible signs of stones after finishing the top screed. The
top screed binder shall also serve as the waterproof top surface.
13. Cleaning -Clean the surrounding area and pour water on the finished
expansion joint. Allow to cure to about 15 to 30 minutes depending on the
ambient condition of the surrounding. The road could be immediately opened
to traffic after cooling.
415.5 Method of Measurement
The installed expansion joint will be measured by the cubic meter (m3). The
quantity to be paid for shall be the volume in-placed as shown on the Plans
and accepted by the Engineer.
415.6 Basis of Payment
The accepted quantities, measured as prescribed in Section 415.5, shall be
paid for at the contract unit price for the expansion joint which price and
payment shall be full compensation for furnishing and placing all
materials, including labor, equipment, tools and incidentals necessary to
complete the work prescribed in this Item.
Payment will be made under:
Pay Item Number
|
Description
|
Unit of Measurement
|
415
|
Elastomeric, HotApplied Expansion Joint Sealant (with
Single-Sized
Aggregates)
|
Cubic meter
|
Post a Comment