ITEM 515- MECHANICALLY-STABILIZED EARTH (MSE) RETAINING WALLS
515.1 Description
    
This item shall consist of furnishing materials and placement of
    Mechanically-Stabilized Earth (MSE) retaining walls constructed in
    accordance with these specifications and in reasonably close conformity to
    the lines, grades, design and dimensions shown on the Plans.
The Mechanically-Stabilized Earth (MSE) retaining walls shall consist of a
    non-structural leveling pad, facing panels, and soil reinforcement elements
    mechanically connected to each facing panel. Soil reinforcement shall have
    sufficient length, strength, and frictional resistance as required by the
    design.
515.2 Material Requirements 
515.2.1 Concrete Leveling Pad
Concrete leveling pad shall be Class A as specified in Item 405, Structural
    Concrete, unless otherwise specified or required by the Engineer.
515.2.2 Geotextile
Geotextile shall be specified in Item 715, Geotextiles, unless otherwise
    specified or required by the Engineer.
        515.2.3 Mechanically-Stabilized Earth (MSE) Retaining Wall Mate
    
Mechanically-Stabilized Earth (MSE) retaining wall material shall conform
    to the following, unless otherwise specified in the Contract.
515.2.3.1 Concrete Face Panels 
Concrete shall conform to Item 405, Structural Concrete, unless otherwise
    specified or required by the Engineer.
Reinforcing steel bars shall be as specified in Item 404, Reinforcing,
    Steel, unless otherwise specified or required by the Engineer.
Concrete shall have a minimum compressive strength of 30 MPa at 28 days.
Concrete panels shall be fully supported until the concrete has reached a
    minimum compressive strength of 7 MPa. The concrete panels shall be shipped
    and installed after the concrete has reached a minimum compressive strength
    of 24 MPa.
Concrete facing panels shall have a minimum thickness of 140 mm and a
    minimum concrete cover on reinforcing steel of 37.5 mm.
The panels shall be cast face down in level forms supported on a flat
    working surface. Guides shall be used to locate and support attachment
    devices set in the back face of the panel. The concrete in each panel unit
    all be placed without interruption and shall be consolidated by the use of
    an approved vibrator, supplemented by such hand tamping as may be necessary
    to force the concrete into the corners of the forms and to prevent the
    formation of stone pockets or cleavage planes. Clear form oil or release
    agent shall be used throughout the casting operation.
The rear face of the panel shall be screeded to eliminate open pockets of
    aggregate and surface distortions in excess of 6 millimeters. The panels
    shall be casted on a flat area. Galvanized connecting devices fasteners
    shall not be attached to the face panel steel reinforcement.
The production lot number, date of manufacture and the piece mark shall be
    clearly inscribed on an unexposed face of each panel.
All units shall be handled, stored, and shipped in such a manner as to
    eliminate the dangers of chipping, discoloration, cracks; fractures, and
    excessive bending stresses. Panels in storage shall be supported on firm
    wooden blocking to protect the panel connection devices and the exposed
    exterior finish.
Concrete panels shall be manufactured within the following tolerances:
- Panel dimensions. Position of panel connection devices shall be within 25 millimeters. All other dimensions within 5 millimeters.
 - Panel squareness. Squareness, as determined by the difference between the 2 diagonals, shall · not exceed 13 millimeters.
 - Panel surface finish. Surface defects on smooth formed surfaces 1.5 meters or more in length .shall not exceed 3 millimeters. Surface defects on textured-finished surfaces 1.5 meters or more in length shall not exceed 8 millimeters.
 
Concrete face panels having any or all of the following defects shall be
    rejected.
- Defects that indicate imperfect molding
 - Defects indicating honeycombed or open texture concrete.
 - Cracked or severely chipped panels.
 - Color variation on front face of panel due to excess form oil or other reasons.
 
515.2.3.2 Wire Facing 
Wire facing shall be fabricated welded wire fabric conforming to AASHTO M
    55M, except that Section 7.4 applies for all longitudinal and transverse
    wire sizes. After fabrication wire fabric shall be galvanized according to
    AASHTO M 111 M.
515.2.3.3 Gabions 
Gabions shall conform to Item 511, Gabions and Mattresses, unless otherwise
    specified or required by the Engineer.
515.2.3.4 Backing Mat 
Backing mat shall be fabricated welded wire fabric conforming to AASHTO M
    55M, except that Section 7.4 applies for all longitudinal and transverse
    wire sizes. After fabrication wire fabric shall be galvanized according to
    AASHTO M 111 M.
515.2.3.5 Clevis Connector 
Clevis connector shall be fabricated from cold-drawn steel wire conforming
    to AASHTO M 32M, and welded according to AASHTO M 55M. After fabrication
    clevis connector shall be galvanized according to AASHTO M 111M.
515.2.3.6 Connector Bars 
Connector bars shall be fabricated from cold-drawn steel wire conforming to
    AASHTO M 32M and shall be galvanized according to AASHTO M 111M.
515.2.3. 7 Fasteners 
Fasteners shall be made of 13-millimeter diameter, heavy head bolts, nuts,
    and washers conforming to AASHTO M 164M and shall be galvanized according
    to AASHTO M 232.
515.2.3.8 Hardware Cloth
 
    Hardware cloth shall be fabricated with maximum 7-millimeter square mesh
    openings from woven or welded galvanized steel wire fabric conforming to
    ASTM A 740.
515.2.3.9 Reinforcing mesh
 
    Reinforcing mesh shall be fabricated from cold-drawn steel wire conforming
    to AASHTO M 32M. Wire shall be welded into the finished mesh fabric
    according to AASHTO M 55M. Wire shall be galvanized according to AASHTO M
    111 M after fabrication. Damaged galvanized coating shall be repaired
    before installation.
515.2.3.10 Reinforcing strips 
Reinforcing strips shall be fabricated from high-strength, low alloy
    structural steel conforming to ASTM A 572M, grade 450, type-3. Reinforcing
    strips shall be galvanized according to AASHTO M 111 M after fabrication.
515.2.3.11 Tie strip 
Tie strip shall be fabricated from hot-rolled steel conforming to ASTM A
    570M, grade 50. Tie strip shall be galvanized according to AASHTO M 111M.
515.2.4 Select Granular Backfill
Select Granular Backfill shall consist of sound, durable, granular material
    free from organic matter or other deleterious material (such as shale or
    other soft particles with poor durability).
The select granular backfill materials shall conform to Table 515.1,
    Grading Requirements.
Table 515.1 -Grading Requirements:
Sieve Designation Standard (mm)
                 
 | 
            
Percent by Mass Passing Designated Sieve
                 
(AASHTO T/27 and T 11)
                 
 | 
        
100
                 
0.0425
                 
0.075
                 
 | 
            
100
                 
0 - 60
                 
0 -15
                 
 | 
        
The shear angle of internal friction shall not be less than 340.
Compact samples for AASHTO T 236 to 95 percent of the maximum density
    determined according to AASHTO T 99 Method C or D and corrected for
    oversized material according to ASSHTO T 99, Note 9.
If the select granular backfill materials are subjected to five (5) cycles
    of the sodium sulfate soundness test by AASHTO T 104, the weighted loss
    shall not exceed 15 mass percent.
The material shall have a Plasticity Index of not more than 6 as determined
    by AASHTO T 90.
Electrochemical requirements for Mechanically-Stabilized Earth (MSE)
    retaining walls with metallic reinforcements shall comply with the
    following requirements:
Test
                 
 | 
            
Requirements
                 
 | 
        
Resistivity, AASHTO T 288
                 
pH, AASHTO T 289
                 
Sulfate Content, AASHTO T 290 Chloride Content, AASHTO T
                    291
                 
 | 
            
3000 'Ω-cm min.
                 
5.0 to 10.0
                 
200 ppm max.
                 
100 ppm max.
                 
 | 
        
Note:
    Tests for sulfate and chloride content are not required when resistivity is
    greater than 5,000 Ohm centimeters.
Electrochemical requirements for Mechanically-Stabilized Earth (MSE)
    retaining walls with Geosynthetic reinforcements, specify that the pH shall
    be between 5.0 to 10.0 as determined by AASHTO T 289.
515.2.5 Structural Backfill
Structural backfill shall consist of free draining granular materials free
    from excess moisture, muck, frozen lumps, roots, sod, or other deleterious
    material.
The structural backfill materials shall conform to Table 515.2 Grading
    Requirements.
Table 515.2 - Grading Requirements
Sieve Standard Designation(mm)
                 
 | 
            
Percent by Mass Passing (AASHTO Designated T 27 and Sieve T
                    11)
                 
 | 
        
75
                 
0.075
                 
 | 
            
100
                 
15 max
                 
 | 
        
The material shall have a liquid limit of not more than 30 as determined by
    AASHTO T 89.
515.3 Construction Requirements
515.3.2 General
Survey and verify the limits of the wall installation. Detailed working
    drawings such as but not limited to wall elevations, soil reinforcement
    length for each section of wall, applied bearing pressure, facing panel
    layout, and representative typical details and supporting calculations of
    the Mechanically-Stabilized Earth (MSE) retaining walls shall be furnished
    by the Contractor to the Engineer at least three (3) weeks prior to
    construction. Construction shall not start until the Engineer has reviewed
    and approved the design/Plans.
Mechanically-Stabilized Earth (MSE) retaining walls design shall be in
    accordance with DPWH – Design Guidelines Criteria and Standards (Latest
    Edition)
A minimum horizontal bench1.20 meters wide shall be provided in front of
    walls founded on slopes.
515.3.2 Excavation
The ground shall be excavated in accordance with the dimensions, lines and
    grades shown on the Plans. Excavation shall be I accordance whenever
    applicable, with Section 103.2, Excavation.
Level and layout the foundation for a width equal to the length of
    reinforcing elements plus 0.5 meter. When a rocky foundation is situated
    anywhere along the wall, place 150 millimeters of select granular backfill
    materials under the reinforcing mesh or strips.
515.3.3 Foundation Preparation
Prior to wall construction, the foundation, if not on rock surface shall be
    compacted as directed by the Engineer. Any unsuitable foundation material,
    as determined by the Engineer, shall be excavated and replaced with
    granular material, and shall be compacted in accordance with Section
    515.3.5, Backfilling.
The construction requirements for concrete leveling pad shall be in
    accordance, whenever applicable, with Section 1405.3, Structural Concrete.
    Allowable elevation tolerances are + 3.0 mm and - 6.0 mm from the design
    elevation.
515.3.4 Wall Erection 
Walls shall be erected in accordance with the approved shop drawings and
    the manufacturer's recommendations. When required by the Engineer, an
    experienced field representative from the wall system manufacturer shall be
    present on site during erection.
The starting point for the wall erection shall be as shown on the Plans or
    if the new wall matches an existing wall. Otherwise the wall shall begin on
    the leveling pad at the lowest elevation.
The concrete leveling pad shall be allowed to cure for at least 12 hours
    before the wall erection.
515.3.4.1 Concrete-Faced-Walls
Where walls or wall sections intersect at an angle of 130° or less, a
    special vertical corner element panel shall be used. The corner element
    panel shall cover the joint of the panels that abut the corner, to allow
    for the independent movement of the abutting panels.
Standard facing panels shall have at least two levels of earth
    reinforcements to stabilize the panels against rotation. Top and bottom
    half panels shall have at least one (1) level of earth reinforcements. The
    wall facing shall be designed to accommodate differential settlement of one
    (1) meter in one hundred (100) meters. The spacing between adjacent panels
    shall be designed to be 19 millimeters. Joints between panels shall have a
    ship lap configuration to protect the joint materials from vandalism. There
    shall be no openings through the wall facing except for utilities to pass
    through the wall. Slip joints to accommodate excessive differential
    settlement shall be included if indicated in the Plans.
515.3.4.1.1 Installation 
Precast facing panels shall be erected by means of lifting devices
    connected to the upper edge of the panel. Precast facing panels shall be
    aligned within 19 millimeters vertically and horizontally when measurement
    with a 3-meter straightedge.
Joint openings shall be 19±6 millimeters wide. Joint material shall be
    installed according to the drawings. All joints at the backside of the
    panels shall be covered with a 300-millimeter wide strip of geotextile.
    Geotextile splices shall be overlapped with a minimum of 100 millimeters.
The panels in position shall be supported with temporary wedges or bracing
    during backfilling operations. The final position of the wall shall have
    maximum overall vertical tolerance (top to bottom) of 13 millimeters per 3
    meters of wall height.
515.3.4.2 Wire-faced Walls 
Place backing mats and 6-millimeter hardware cloth in successive horizontal
    lifts as backfill placement proceeds. Connect, tighten, and anchor soil
    reinforcement elements to the wall facing units before placing backfill. An
    individual lift shall have a maximum vertical tolerance and an overall wall
    (top to bottom) vertical tolerance of 25 millimeters per 3 meters of wall
    height. Reinforcement elements shall be placed within 25 millimeters
    vertically above the corresponding connection elevation at the wall face.
    Reinforcing elements shall not be placed below the corresponding connection
    elevations. Designed batter of the wall shall not deviate by more than 25
    millimeters per 3 meters· of wall height. Deviation of more than 50
    millimeters shall not be allowed at any point in the wall from 3-meter
    straightedge placed horizontally on the theoretical plane of the design
    face.
The minimum wall embedment shall be 300 mm unless otherwise shown on the
    Plans or as established by the Engineer.
515.3.4.3 Gabion-Faced Walls
The construction requirements of gabions shall be in accordance whenever
    applicable, with Section 511.3, Gabions and Mattresses.
The first lift of backfill shall be placed before, filling the gabion
    baskets. Reinforcement mesh shall be laid horizontally on compacted fill
    and normal to the face of the wall. The gabion facing unit shall be
    connected to the reinforcement mesh with spiral binders or tie wire at
    100-millimeter nominal spacing with alternating single and double locked
    loops. Reinforcement mesh taut shall be pulled and anchored before placing
    additional backfill.
515.3.5 Backfilling 
The stabilized volume shall be backfilled with select granular backfill.
    The maximum compacted thickness of any layer shall not exceed 150 mm. All
    subsequent layers shall be spread and compacted in a similar manner.
The backfill materials shall be compacted until a uniform density of not
    less than 95 mass percent of the maximum dry density determined by AASHTO T
    99 Method C is attained, at a moisture content determined by the Engineer
    to be suitable for such density. Acceptance of compaction may be based on
    adherence to an approved roller pattern developed as set forth in Item 106,
    Compaction Equipment and Density Control Strips.
During the progress of the Work, the Engineer shall make density tests of
    compacted material in accordance with AASHTO T 310 or other approved field
    density tests. If, by such tests, the Engineer determines that the
    specified density and moisture conditions have not been attained, the
    Contractor shall perform additional work as may be necessary to attain the
    specified conditions.
At least one group of three (3) in-situ density tests shall be carried out
    for each 500 m of each layer of compacted fill.
Backfilling shall be even on all sides of the structure, and each layer
    shall be extended to the limits of the excavation or to natural ground.
Backfill shall be placed in such a manner as to avoid any damage or
    disturbance to the wall materials or misalignment of the facing panels. Any
    wall materials which become damaged or disturbed during backfill placement
    shall either be removed and replaced at the Contractor’s expense or
    corrected, as directed by the Engineer.
Backfill shall not be placed against concrete less than 7 -days old or
    until 80 percent of the design strength is achieved.
Ensure that no voids exist below the reinforcing mesh or strips. An
    acceptable lightweight mechanical or vibratory compactor shall be used
    within one (1) meter of the wall face. The specified lift thickness shall
    be adjusted as warranted by the type of equipment actually used and as
    approved by the Engineer, but no soil density tests need be taken within
    this area. Where the stabilized volume supports spread footings for bridges
    or other structural loads, the top 1.5 meters shall be compacted to at
    least 100 percent of the maximum density.
Facing or reinforcing elements shall not be damaged or disturbed during
    backfilling. Equipment shall not be operated directly on top of the
    reinforcing mesh or strips. The Contractor shall correct damaged
    misaligned, or distorted wall elements.
Backfill and compact behind the stabilized volume with structural backfill
    in the same methodology done on select granular backfill. At the end of the
    day's operation, the last lift of backfill shall be sloped away from the
    wall face to direct surface runoff away from the wall. Temporary drainage
    shall be constructed to divert any surface runoff from adjacent areas to
    enter the wall construction area.
515.3.6 Placement of Reinforcements
Prior to placing the first layer of reinforcements (strips, mats or grids),
    backfill shall be placed and compacted in accordance with Section 515.3.5,
    Backfilling.
Bending of reinforcements in the horizontal plane that results in a kink in
    their alignment shall not be allowed. Gradual bending in the vertical
    direction that does not kink the reinforcements is allowable.
Connection of reinforcements to piles or bending of reinforcements around
    piles shall not be allowed. Cutting of reinforcement longitudinal bars
    shall not be allowed to avoid conflicts with piles or utility obstructions.
    A structural connection (yoke) from the wall panel to the reinforcement
    shall be used whenever it is necessary to avoid cutting or excessive
    skewing of reinforcements due to pile or utility conflicts.
Soil reinforcements shall be placed normal to the face of the wall, unless
    otherwise shown on the Plans or as directed by the Engineer. If skewing of
    the soil reinforcements is required due to obstructions in the reinforced
    fill, rotatable connections shall be used and the maximum skew angle shall
    not exceed 15 degrees from the normal position unless specifically
    addressed in design calculations that justify that the skewed
    reinforcements are adequate.
515.4 Method of Measurement 
The area to be paid for under this item shall be the .number of square
    meters (m2) of Mechanically-Stabilized Earth (MSE) retaining
    walls furnished, placed and accepted. The area shall be measured on the
    facial area of the walls installed. The wall surface area shall include the
    surface area of nominal panel joint openings and wall penetrations such as
    pipes and other utilities. The payment will include Mechanically-stabilized
    earth walls, backing mat, clevis connector, connector bars, fasteners,
    hardware cloth, reinforcing mesh, tie strips and other such materials
    contained within or attached to the mechanically-stabilized earth walls.
515.4.1 Other Items 
The quantities of other Contract items which enter into the completed and
    accepted structure will be measured for payment in the manner prescribed
    for the several items involved.
515.4.2 Select Granular Backfill/ Structural Backfill 
Select Granular Backfill/Structural Backfill material, when specified in
    the Contract as a Pay Item shall be measured in cubic place by the meter,
    completed and accepted. Cross-sectional measurements shall not exceed the
    net dimensions shown on the Plans or as directed by the Engineer.
515.4.3 Excavation 
Excavation for Mechanically-Stabilized Earth (MSE) retaining walls shall be
    measured and paid for as provided in Item 103, Structure Excavation.
515.4.4 Concrete 
Concrete leveling pad/ concrete panels for mechanically-stabilized earth
    (MSE) retaining walls shall be measured and paid for as provided in Item
    405, Structural Concrete.
515.4.5 Gabions 
Gabions for Mechanically-Stabilized Earth (MSE) retaining walls shall be
    measured and paid for as provided in Item 511, Gabions and Mattresses.
515.5 Basis of Payment 
The accepted quantities, measured as prescribed in Section 515.4 shall be
    paid for at the contract unit price for each particular item listed below
    that is included in the bill of quantities which price and payment shall be
    full compensation for furnishing and placing all materials including the
    use of equipment and tools, labor and incidentals necessary to complete the
    work.
Payment will be made under:
| Pay item Number | Description | Unit of Measurement | 
| 515 (1)
                 515 (2) 515 (3)  | 
            Mechanically-Stabilized Earth (MSE) Retaining Walls
                 Select Granular Backfill Structural Backfill  | 
            Sq.m.
                 Cu.m. Cu.m.  | 
        