ITEM 610 – SODDING
610.1 Description
This Item shall consist of furnishing and laying of live sod on the
shoulders, slopes, ditches, or other locations as designated, construction
of sod ditch checks or similar appurtenances, as shown on the Plans or as
ordered and laid out in the field by the Engineer, all in accordance with
this Specification.
610.2 Material Requirements
The sod shall consist of healthy, dense, well-rooted growth of permanent
and desirable grasses indigenous to the general locality where it is to be
used and shall be free from weeds or undesirable grasses. At the time the
sod is cut, the grass on the sod shall have a length of approximately 50 mm
(if longer, the grass shall be cut to approximately this length) and the
sod shall have been raked free from debris.
The sod shall be cut into uniform squares approximately 300 mm x 300 mm,
but not larger than is convenient for handling and transporting.
The thickness of the sod shall be uniform as possible approximately 40 mm
or more depending on the nature of the sod, so that practically all of the
dense root system of the grasses will be retained, but exposed, in the sod
strip and that the sod can be handled without undue tearing or breaking.
In the event the sod to be cut is in a dry condition as to cause scrumbling
or breaking during cutting operations, the Contractor, at his own expense,
shall apply water in sufficient quantities at least 12 hours before cutting
to provide a well-moistened condition of the sod to the depth to which it
is to be cut. Sods shall be subject to the approval of the Engineer.
610.3 Construction Requirements
610.3.1 Preparation of the Earth Bed
The area to be sodded shall be constructed to the required cross-section
and contour, and the tops and bottoms of the slopes shall be rounded as
shown in the typical roadway sections.
The areas to be sodded shall be free from stones, roots or other
undesirable foreign materials.
The soil on the area to be sodded shall be loosened and brought to a
reasonably fine texture to a depth of not less than 30 mm by means of
equipment on hand methods adapted for the purpose.
610.3.2 Placing the Sod
The earth bed upon which the sod is to be placed shall be moistened to the
loosened depth, if not naturally sufficiently moist, and the sod shall be
placed thereon within 24 hours after the same has been cut.
Unless otherwise required, the sod on slopes shall be laid on horizontal
strips beginning at the bottom of the slope and working upwards. When
placing sod in ditches, or in the construction of sod ditch checks or
similar appurtenances, the length of the strips shall be laid at right
angles to the direction of the flow of the water.
Sod shall be laid so that the joints caused by abutting ends of sod strip
are not continuous. Each sod strip shall be so laid as to abut snugly
against the strip previously laid.
As the sod is being laid it shall be lightly tamped with suitable wooden or
metal tampers sufficiently to set or press the sod into the underlying
soil.
At points where it is anticipated that water may flow over a sodded area,
the upper edges of the sod strips shall be turned into the soil to be below
the adjacent area and a layer of earth place over this juncture and
thoroughly compacted. At the limits of sodded areas, the end strips shall
be turned in and treated similarly.
610.3.3 Staking the Sod
On all slopes steeper than one vertical to four horizontal, sod shall be
pegged with stakes 200-300 mm in length, spaced as required by the nature
of the soil and steepness of slope. Stakes shall be driven into the sod at
right angles to the slope until flush with the bottom of the grass blades.
610.3.4 Top Dressing
After staking has been completed, the surface shall be cleared of loose
sod, excess soil or other foreign material, whereupon a thin layer of
topsoil shall be scattered over the sod as a top dressing and the areas
shall then be thoroughly moistened by sprinkling with water.
610.3.5 Watering
The Contractor shall regularly water and maintain sodded areas in a
satisfactory condition for the duration of the Contract and until final
acceptance of the work by the Engineer.
610.4 Method of Measurement
Sodding shall be measured by the square meter and the quantity to be
measured for payment shall be the actual number of square meters of area on
which sod has been placed in accordance with this Specification and within
the limits of construction as designated on the Plans or as ordered by the
Engineer.
610.5 Basis of Payment
The quantity as determined in Subsection 610.4, Method of Measurement,
shall be paid for at Contract unit price per square meter for Sodding which
price and payment shall be full compensation for preparing the earth bed,
for furnishing, placing, staking, top dressing and watering the sod, and
for all labor, equipment, tools and incidentals necessary to complete the
Item.
Payment will be made under:
Pay Item No.
|
Description
|
Unit of Measurement
|
610
|
Sodding
|
Square Meter
|
Post a Comment