ITEM 608 – TOPSOIL
608.1 Description
This Item shall consist of topsoil furnished, transported and spread, or
topsoil removed from designated areas, hauled and spread, in accordance
with this Specification at the location shown on the Plans or as required
by the Engineer.
608.2 Material Requirements
Topsoil furnished shall consist of fertile friable soil of loamy character
without admixture of undesirable subsoil, refuse or foreign materials. It
shall be obtained from well-drained arable land and shall be reasonably
free from roots, hard clay, coarse gravel, stones larger than 50 mm in
size, coarse sand, noxious seeds, sticks, brush, litter and other
deleterious substances. Topsoil shall be capable of sustaining healthy
plant life and shall be subject to the approval of the Engineer.
Topsoil shall contain not less than five (5) percent organic matter as
determined by loss or ignition of samples oven-dried to constant weight.
608.3 Construction Requirements
608.3.1 Sources of Material
Topsoil shall be obtained as specified in Item 102, Excavation, or from
other approved sources. The Contractor shall notify the Engineer at least
five days before he intends to start topsoil stripping operations. After
inspection and approval by the Engineer and prior to stripping any topsoil,
the Contractor shall remove noxious weeds and tall grass, brush roots and
stones larger than 50 mm in diameter.
608.3.2 Placing
The topsoil shall be evenly spread on the areas and to the line and level
shown on the Plans and compacted with a light roller to a depth of not less
than 100 mm. Spreading shall not be done when the ground topsoil is
excessively wet, or otherwise in a condition detrimental to such work. The
roadway surfaces shall be kept clean during hauling and spreading
operations.
After spreading has been completed, large clods, stones, roots, stumps and
other loose-lying materials shall be raked up and removed. Any erosion,
irregularities of grade or other incidental damage to the surface of the
topsoil shall be repaired and/or restored to the Engineer’s satisfaction.
608.4 Method of Measurement
The quantities to be paid for shall be the number of cubic meters of
Topsoil removed, furnished and hauled complete in place and accepted.
608.5 Basis of Payment
The quantities, as determined in Subsection 608.4, Method of Measurement,
shall be paid for at the contract unit price respectively, for each of the
particular Pay Items listed below that is shown on the Bid Schedule, which
price and payment shall be full compensation for furnishing and placing all
materials and for all labor, equipment, tools and incidentals necessary to
complete the Item.
Payment will be made under:
Pay Item Number
|
Description
|
Unit of Measurement
|
608(1)
608(2)
|
Furnishing and Placing Topsoil
Placing Topsoil
|
Cubic Meter
Cubic Meter
|
Post a Comment